It is vital we achieve a level of consistency in the identification of nonconformities, and in the reporting of them.
We have two categories of non-conformity.
Within the audit process it is important to acknowledge and identify positive findings.
This could include for example, excellence in management of statutory and regulatory requirements, best in class standard operating procedures or where factors of risk and opportunities have really been embraced by the organisation.
Clearly, this demonstrates that top management commitment and involvement.
A single identified lapse or minor omission, which would not in itself lead to the organisation’s management system failing to achieve its intended output.
There may be a requirement to identify a non-conformity situation this will be based on the definition of a non-conformity taken from ISO9000, which is: nonconformity
non-fulfilment of a requirement (3.6.4)
Note 1 to entry: This constitutes one of the common terms and core definitions for ISO management.
If there is no audit evidence – there is no nonconformity. If the auditor cannot identify a requirement, then the auditor cannot raise a nonconformity.
The next step the auditor will need to take is to identify and record the specific requirement.
that is not being met. Remember, a nonconformity is non-fulfilment of a requirement
A breakdown or failure to fulfil one or more requirements of the management system standard to effectively control the processes for which it was intended, or a situation where nonconforming product or service would be delivered, or a situation that raises significant doubt about the ability of the organisation’s management system to achieve its intended outputs.
A breakdown or failure to fulfil one or more requirements of the management system standard to effectively control the processes for which it was intended, or a situation where nonconforming product or service would be delivered, or a situation that raises significant doubt about the ability of the organization’s management system to achieve its intended outputs.
However, nonconformities are only raised when the assessor finds objective evidence to support the nonconformity, and all raised must reference the observed deviation with objective evidence described as well as the requirement in terms of standard or client procedure.
During an audit an observation may be made. This is where is insufficient information is available for example, this could be ref to clause 9.3 where a management review meets all the requirements of the standard in relation io inputs to outputs but the commentary in the management review could bee seen to require further elaboration.
During an observation may also be applicable to comment on good practice seen within the management system and various process activities.
During a precertification assessment, which is otherwise known as a’ document review’ the word observation is used other than nonconformity.
Observations can only be raised for an ineffective process. A nonconformity cannot be downgraded to an observation which can be termed as soft grading.
For example, insufficient detail within management review, ineffective process efficiency, high levels of defect rates.
At the end of an assessment and prior to the assessment team leaving site, it is best practice to leave a report.
The assessor will verbally inform the client/auditee of any conclusions, non conformities and observations.
The report may be in either paper or electronic but must contain all the key aspects as required in an audit report and left with the auditee.
Note, The audit report will be part of the case study.
The audit report is applicable to various interested parties and their needs, which could include:
The audit report should introduce the organisation, and executive summary, reference to management commitment and leadership. Actions taken from previous audits, review of internal audits and management review. References to continual improvement .
Clear illustration of any significant changes, audit criteria , reference to any operational activity where applicable to compliance and legal compliance, audit methodology and continuing effectiveness of the management system. Use of Marks or any reference to certificates.
Issues requiring further attention, the audit report should audit should also include a disclaimer.
See ISO17021 for the full requirements.
What should go in a typical Audit Report (external)
A) identification of the certification body;
b) the name and address of the client and the client’s representative;
c) the type of audit (e.g. initial, surveillance or recertification audit or special audits);
d) the audit criteria;
e) the audit objectives;
f) the audit scope, particularly identification of the organizational or functional units or processes audited and the time of the audit;
g) any deviation from the audit plan and their reasons;
h) any significant issues impacting on the audit programme;
i) identification of the audit team leader, audit team members and any accompanying persons;
j) the dates and places where the audit activities (on site or offsite, permanent or temporary sites) were conducted;
k) audit findings (see 6.5.1), reference to evidence and conclusions, consistent with the requirements of the type of audit;
l) significant changes, if any, that affect the management system of the client since the last audit took place;
m) any unresolved issues, if identified;
n) where applicable, whether the audit is combined, joint or integrated;
o) a disclaimer statement indicating that auditing is based on a sampling process of the available information;
p) recommendation from the audit team
q) the audited client is effectively controlling the use of the certification documents and marks, if applicable;
r) verification of effectiveness of taken corrective actions regarding previously identified nonconformities, if applicable.
Actions required to meet customer requirements and satisfaction:
Audits should be aimed at identifying risks and opportunities as well as non-conformance categories and should also be aimed at improving the effectiveness and efficiency in operational management within the organisation and ensuring that they consider the strategic direction and relevant stakeholder needs and expectations.
Improvement is made in ISO 10.3 of ISO 9001 and could take into consideration internal communication, reviewing follow up activities, effectiveness of action taken for non-conformities. Effectiveness of actions taken from management review meetings.
Customer feedback and developing analysis and improvement where relevant, training programmes and training needs analysis.
It is important that we plan the audit effectively in terms of time management for both auditor and auditee to be effective. An audit plan ensures that the allocated time to conduct the assessment is effectively managed.
The auditor has the skills and through a professional approach with integrity should build the rapport with the auditee to ensure an effective approach is undertaken so that both parties can manage the risk and opportunity as part of the audit.
Auditor has the ability to use different audit methods that will include effective interview process and giving the auditee time to explain, at this point the auditor communication skills are essential and this includes the ability to listen.
Explanations can then be validated in terms of “show me via objective evidence” the explanations just given.
Operational Processes
During the assessment it is essential to capture operational controls see section 8 of ISO9001:2015. This will include production and service provision including external support processes. The concept of risk and opportunity must be captured throughout the whole of the quality management system including the context of the organisation and its processes relating to product and service. Throughout operational control it is also a requirement to recognize time management.
When a non-conformity occurs, including any rising from complaints, the organisation shall:
Evaluate the need for action to eliminate the cause(s) of the nonconformity, in order that it does nor recur or occur elsewhere by:
There should be an agreement of the period that corrective action will be sent to the auditor for closure.
In the event of a third-party audit, if a proposed corrective action plan has been dispatched then it should be cross checked with the actual corrective action plan.
There are three parts of a well-documented nonconformity.
1 – the audit evidence to support audit findings
2 a record of requirement to which the non-conformity is detected.
3 A statement of non-conformity, illustrating specific observation
There should be an agreement of the period that corrective action will be sent to the auditor for closure.
In the event of a third-party audit, if a proposed corrective action plan has been dispatched then it should be cross checked with the actual corrective action plan.
The review of actions in response to the non-conformity, management systems auditors are responsible for reviewing the response to non-conformity and verifying the effectiveness of actions taken.
There should be three parts to the response of the organised nonconformity, analysis of cause, correction, and corrective action.
3.12.3
correction
action to eliminate a detected nonconformity (3.6.9)
Note 1 to entry: A correction can be made in advance of, in conjunction with or after a corrective action (3.12.2).
Note 2 to entry: A correction can be, for example, rework (3.12.8) or regrade (3.12.4).
corrective action
action to eliminate the cause of a nonconformity (3.6.9) and to prevent recurrence.
Example of Non-Conformity – Corrective Action Layout
Statement of non-conformity
Quality policy does not capture all requirements from the international standard
Requirement – 5.2.1 Establishing the quality policy
Top management shall establish, implement and maintain a quality policy that:
a) is appropriate to the purpose and context of the organization and supports its strategic direction;
b) provides a framework for setting quality objectives;
c) includes a commitment to satisfy applicable requirements;
d) includes a commitment to continual improvement of the quality management system.
Objective Evidence
The quality policy issue level 2 dates July 12th 2015 does not make any reference to providing a framework for setting the quality objectives.